A2SEA installs first turbine on Dudgeon Offshore Wind Farm

Monday, 9 January, 2017 - 12:00
Sea Challenger and her crew, together with Statoil and Siemens installed the first turbine on Dudgeon OWF. (Photo:Byron Price/Rix Leopard)
Sea Challenger and her crew, together with Statoil and Siemens installed the first turbine on Dudgeon OWF. (Photo: Byron Price/Rix Leopard)

A2SEA’s Sea Challenger installed the first out of the 67 Siemens 6 MW turbines on the 402 MW Dudgeon Offshore Wind Farm for Statoil, Masdar and Statkraft.

For the next months, the vessel will install the turbines being shipped from Green Port Hull in the UK. This is the first time, the Port of Hull will be used as load out port for an offshore wind project.

Since September 2016, Sea Challenger has been used for offshore accommodation during completion and commissioning of the offshore substation. The vessel was jacked up to 20 m above sea level and had accommodation for 80 persons including the A2SEA crew.

Jens Frederik Hansen CEO at A2SEA, said: ”We have wide experience in handling the Siemens 6 MW turbines, but it cannot be done without good team work. It is a great pleasure to once again work together with Siemens, but also our renewed cooperation and partnership with Statoil, which started on their first offshore wind project Sheringham Shoal, and now continues on the Dudgeon
project.”

The Dudgeon Offshore Wind Farm is owned by Statoil (35%), Masdar (35%) and Statkraft (30%) and is situated 32 km off the coast of the seaside town of Cromer in North Norfolk in the UK. When fully commissioned by 2017, the Dudgeon Offshore Wind Farm will provide well over 400,000 households with renewable power.

Silke Funke / A2 SEA

Similar Entries

The first turbine jacket foundation is installed at the Seagreen Wind Farm site, 27 kilometres off the coast of the county of Angus in Scotland (pict: SSE Renewables)

The first turbine jacket foundation has been installed at Seagreen – Scotland’s largest and the world’s deepest, fixed bottom offshore wind farm.

The jacket, which will support the offshore platform substation, was secured on the seabed using the Saipem 7000 heavy lift vessel  (pict. SSE plc)

Construction of the world’s deepest fixed bottom offshore wind farm, which is also Scotland’s largest, has reached another milestone with the installation of a jacket in preparation for the project’s offshore substation topside which is due to be installed in early 2022.

Wind turbine (pict. Dewesoft d.o.o.)

The energy company Vattenfall has selected Dewesoft to provide the tower monitoring solution at what will be the world’s largest offshore wind farm.

First transformer has been delivered to convertor station for Dogger Bank Wind Farm. Image source Dogger Bank Wind Farm (pict. SSE Renewables)

The first of a number of transformers that will enable the transmission of renewable energy from the world’s largest offshore wind farm has been delivered. The transformers will play an integral role in the operation of three onshore convertor stations in East Riding of Yorkshire and on Teesside, that will eventually convert the current from the wind farm for transmission via the national grid network to 6 million UK homes.