EnBW speeds up offshore wind: Investment decision on next offshore wind farm taken

Tuesday, 9 May, 2017 - 14:30

Karlsruhe – EnBW Energie Baden-Württemberg AG has increased the pace at which it is expanding wind energy at sea: Just a few days after having its bid for the 900 megawatt project EnBW He Dreiht accepted in Germany's first offshore wind power auction, the company's Supervisory Board has now given the green light for the next offshore wind farm EnBW Albatros and approved the final decisions taken regarding construction and investment.

EnBW Albatros already has binding approval for connection to the grid and will now be constructed together with the offshore wind farm EnBW Hohe See (497 megawatts) that was approved in December 2016. Albatros will feature 16 turbines of type Siemens SWT-7.0-154 and will have an installed capacity of 112 megawatts. EnBW will realise both wind farms by 2019 as a joint project with a capacity of around 610 megawatts. This marks another milestone for the company from Karlsruhe in its strategic orientation towards renewable energies and will be its fourth offshore wind farm.

EnBW Albatros is located in the so-called "exclusive economic zone" of the North Sea in the immediate vicinity of the EnBW wind farms Hohe See and He Dreiht on an area covering 11 square kilometres. After the scheduled commissioning of the wind farms in 2019, Hohe See and Albatros will together generate around 2.5 billion kilowatt hours of electricity annually. This energy can supply around 710,000 households and save around 1.9 million tonnes of CO2. The electricity generated by Albatros and Hohe See will thus cover the aggregate electricity requirements of all private households in Munich – Germany's third largest city.

The supply contracts for all main infrastructure work for Albatros have already been concluded. The issuing of the notice to proceed to the suppliers also signals the start of the construction, installation and commissioning of the offshore wind farm. Siemens AG has been appointed general contractor for the turbines, foundations and, for the first time, the transformer station. The Dutch company GEOSEA NV is the subcontractor responsible for the foundations. The contractual partner for the array cabling at the wind farm is VBMS GmbH.

Source: EnBW

Similar Entries

Nezzy² in Hymendorf (pict. EnBW/Jan Oelker)

Two wind turbines on a precast concrete floating platform: that, basically, is Nezzy2. This 18 metre tall, 1:10-scale prototype is being tested by EnBW and aerodyn engineering, a north German engineering company, in a flooded gravel pit near Bremerhaven. Next, this summer, Nezzy2 is to prove itself in wind and wave conditions in the Baltic Sea.

EnBW Offshore Windpark Baltic 2 (pict. EnBW)

One of Germany’s largest offshore wind farms in the Baltic Sea, EnBW Baltic 2, is to be serviced from August 2020 from the Danish port of Klintholm on the island of Møn. Until now, the company’s service team – up to 25 in number – have travelled from Rostock to a hotel vessel close to the wind farm.

Liebherr TCC 78000 heavy-duty crane loads 72 monopiles for the largest Danish offshore wind farm "Kriegers Flak" (pict. Liebherr)

Liebherr heavy-duty crane TCC 78000 loads 72 monopiles for the largest Danish offshore wind farm "Kriegers Flak.

Windea Offshore, together with its partner WP Systems, has taken another step towards establishing the WINDEA Blade Service concept. Last week the operation of the working platform System terra was successfully demonstrated at a Siemens SWT-3.6 offshore test turbine in the German district of Nordfriesland.

 
 
 

Contact