First Monopiles for Hornsea Project 1 have left EEW SPC

Sunday, 21 January, 2018 - 16:00

The first six monopiles for the Ørsted project Hornsea Project 1 were loaded at the quay in Rostock from 18th to 21st December 2017. With the crane vessel „SVENJA“ from the company SAL Heavylift the foundations, which are all about 65 m long and weigh 800 tonnes each, will now be on the way to Able Seaton Port in Great Britain, where they will be temporarily stored until installation commences.

The production at EEW SPC is exactly on schedule. The first 48 monopiles have to be shipped by the end of January 2018. EEW SPC will be ready for load out three weeks earlier.

In total EEW SPC will produce 174 monopile foundations, with each having a diameter of 8.1 metres. The largest offshore wind project to date is intended to deliver electricity for well over one million households from 2020.

Source: EEW SPC

Similar Entries

Liebherr TCC 78000 heavy-duty crane loads 72 monopiles for the largest Danish offshore wind farm "Kriegers Flak" (pict. Liebherr)

Liebherr heavy-duty crane TCC 78000 loads 72 monopiles for the largest Danish offshore wind farm "Kriegers Flak.

Loadout of the two monopiles and transition pieces at EEW SPC quay in Rostock

EEW Special Pipe Constructions GmbH, a member of the EEW Group, has announced the successful fabrication of two heavy monopile foundations and two transition pieces for the Coastal Virginia Offshore Wind (CVOW) demonstration project.

MHI Vestas and Total formally announced their involvement in the Eolmed project this week (pict. Ideol)

MHIV and Total formally announced their involvement in the Eolmed project this week. These internationally recognized leaders and the project developer QAIR have agreed to combine their respective know-how’s and efforts to successfully develop and execute this 30MW pilot project.

EnBW has awarded the contract in the EU-wide tender for project certification of the EnBW He Dreiht offshore wind farm to Bureau Veritas Industry Services GmbH.