First turbine successfully installed at Nordsee One

Thursday, 9 March, 2017 - 12:30
Installation of first Senvion turbine at Nordsee One was completed according to schedule. (Photo: innogy SE)
Installation of first Senvion turbine at Nordsee One was completed according to schedule. (Photo: innogy SE)

Installation of the 54 Senvion 6 MW wind turbines that will comprise the Nordsee One Offshore Wind Farm has commenced at the base port in Eemshaven.

Two sets of wind turbines each consisting of a fully assembly steel tower, a nacelle and a pre-assembled rotor, were loaded onto the installation vessel MPI Enterprise, which transported the components to the construction site at sea located approximately 40 km north off the island of Juist. Upon arrival at the offshore site, the first of the two turbines was installed using the installation vessel’s own crane.

The nacelles alone weigh-in at approx. 335 tonnes, the tower itself measures almost 70 metres overall in length, and weighs over 240 tonnes. Each rotor blade is 61 meters in length and weighs approximately 20 tonnes.

In April 2016 installation of the turbine foundations was completed. The substation was installed last summer, and the inter-array cable laying was successfully completed in September 2016. Once completed, the Nordsee One wind farm will consist of 54 wind turbines of the type Senvion 6.2M126 with an overall installed capacity of 332 MW. Commissioning of the wind farm is anticipated by the end of 2017. Nordsee One is owned by Northland Power Inc. (85%) and innogy SE (15%).

Pierre Lestienne, Managing Director (CFO) of Nordsee One GmbH explained: “We have reached this important milestone according to schedule and within budget. I'm really proud of this achievement. This outcome is the result of precise planning and efficient execution.”

Tim Kittelhake, Managing Director (COO) of Nordsee One GmbH added: “The team worked together hand-in-hand, so the loading of the first major components at our base port in Eemshaven, as well as the installation at sea, both went very smoothly. We look forward to installation of the next turbines, which will follow immediately. We plan to have all turbines installed and commissioned by the end of this year.”

Northland Power / innogy SE /
Nordsee One / Silke Funke

Similar Entries

The jacket, which will support the offshore platform substation, was secured on the seabed using the Saipem 7000 heavy lift vessel  (pict. SSE plc)

Construction of the world’s deepest fixed bottom offshore wind farm, which is also Scotland’s largest, has reached another milestone with the installation of a jacket in preparation for the project’s offshore substation topside which is due to be installed in early 2022.

The first turbine jacket foundation is installed at the Seagreen Wind Farm site, 27 kilometres off the coast of the county of Angus in Scotland (pict: SSE Renewables)

The first turbine jacket foundation has been installed at Seagreen – Scotland’s largest and the world’s deepest, fixed bottom offshore wind farm.

First transformer has been delivered to convertor station for Dogger Bank Wind Farm. Image source Dogger Bank Wind Farm (pict. SSE Renewables)

The first of a number of transformers that will enable the transmission of renewable energy from the world’s largest offshore wind farm has been delivered. The transformers will play an integral role in the operation of three onshore convertor stations in East Riding of Yorkshire and on Teesside, that will eventually convert the current from the wind farm for transmission via the national grid network to 6 million UK homes.

Edda Wind - Offshore Wind Service Vessels

Following the receipt of equipment orders for four offshore wind service vessels announced in May 2020, MacGregor, part of Cargotec, has received an additional order for another two Commissioning Service Operation Vessels (CSOV) that will further expand the Østensjø Rederi Edda Wind fleet.