In 2017, Mammoet, heavy lifting and transport specialist, has been contracted by Lamprell Energy for the heavy lifting and transport of 60 jacket foundations for the East Anglia One offshore wind farm project.

ScottishPower Renewables’ new £2.5 billion offshore wind farm, East Anglia One, will consist of 102 turbines in the North Sea, each rated at 7 megawatts, totaling an overall generating capacity of 714 megawatts. It is expected to generate power for more than 500,000 British homes every year. Lamprell was awarded the fabrication and supply of 60 jacket foundations and their accompanying piles.

The jackets are placed on the seabed and form a secure platform for wind turbine generators to be fixed to. Under the contract, Mammoet has to perform heavy lifting and upending, weighing, transport and load-out of the jackets at Lamprell’s Jebel Ali, Hamriyah and Sharjah yards in the United Arab Emirates. Once complete, the jackets will be loaded onto a specialist ship bound for Europe.

Michel Bunnik, Mammoet’s Regional Sales Director said: “Mammoet are proud to be the partner of choice for the heavy lift and transport services for Lamprell and excited to have the opportunity to contribute to a project of such a significance”.

Source: Mammoet

Similar Entries

The first turbine jacket foundation is installed at the Seagreen Wind Farm site, 27 kilometres off the coast of the county of Angus in Scotland (pict: SSE Renewables)

The first turbine jacket foundation has been installed at Seagreen – Scotland’s largest and the world’s deepest, fixed bottom offshore wind farm.

First transformer has been delivered to convertor station for Dogger Bank Wind Farm. Image source Dogger Bank Wind Farm (pict. SSE Renewables)

The first of a number of transformers that will enable the transmission of renewable energy from the world’s largest offshore wind farm has been delivered. The transformers will play an integral role in the operation of three onshore convertor stations in East Riding of Yorkshire and on Teesside, that will eventually convert the current from the wind farm for transmission via the national grid network to 6 million UK homes.

The jacket, which will support the offshore platform substation, was secured on the seabed using the Saipem 7000 heavy lift vessel  (pict. SSE plc)

Construction of the world’s deepest fixed bottom offshore wind farm, which is also Scotland’s largest, has reached another milestone with the installation of a jacket in preparation for the project’s offshore substation topside which is due to be installed in early 2022.

Deployment of a patent protected 4T Filter Unit Rockbag on Saint Nazaire Offshore Wind Farm (pict. Ridgeway)

Saint-Nazaire Offshore Wind Farm will use Ridgeway Rockbags for cable stabilisation and protection.