Nearshore project Nordergründe put into operation

Wednesday, 20 December, 2017 - 14:45
wpd and the co-shareholders of the Nordergründe John Laing Group plc and the Gothaer Insurance Group announced that installation work has now been successfully completed. (Photo: wpd)
wpd and the co-shareholders of the Nordergründe John Laing Group plc and the Gothaer Insurance Group announced that installation work has now been successfully completed. (Photo: wpd)

The last of a total of 18 turbines of the 111 MW wind farm Nordergründe was connected to the grid  under the project management of the Bremen developer wpd.

Building work on the nearshore wind farm kicked off in May 2016: The first monopile for the Senvion turbines of the type 6.2M126 was set up 15 kilometres north-east of Wangerooge in the Weser estuary. All foundation structures had been completely installed in the mid of 2016. This was directly followed by installation of the wind turbines, which was completed at the beginning of December 2016.

The project faced with a serious challenge in September 2016 when the manufacturer of the offshore substation surprisingly filed for insolvency. A quick solution had to be found as to how further construction was to continue on the structure, which at that time consisted merely of a rough steel structure. “After analysing various possibilities, we decided together with banks and equity investors that completion of the construction should be managed by wpd alone“, explains Achim Berge Olsen, Managing Director of OWP Nordergründe GmbH & Co. KG and wpd offshore GmbH. In accordance with the revised programme, wpd completed installation of the substation at the end of September 2017. Since then work has involved successive commissioning of each individual turbine. “Yesterday was a special day for all of us. We are very happy to have successfully completed the project,” says Berge Olsen.

Nordergründe wind farm is located in water depths of up to ten metres within the 12-nautical mile zone of the German North Sea. Grid connection is facilitated by a single connection via the grid operator, Tennet. Manufacturers of the components for the wind farm originate from the German north-west region. In addition to Senvion (wind turbines) these include Ambau (foundations), NSW (internal wind farm cabling) and Bilfinger Marine & Offshore Systems, now Van Oord (installation). In future, Deutsche Windtechnik will assume operational management of the wind farm.

wpd / Funke

 

Similar Entries

Rostock-based company EEW Special Pipe Constructions GmbH has received an order from the Swedish energy group Vattenfall to produce 41 monopiles for the 344 MW offshore wind
farms Vesterhav. The contract was signed on 19 November 2021.

The first monopile for the Baltic Eagle offshore wind project is finished (pict. EEW SPC)

On 18 February 2022, the first monopile for the Baltic Eagle offshore wind farm was completed. The pile weighs 1,363 tonnes with a diameter of 9 metres. Baltic Eagle is already the second wind farm project of the Spanish energy company Iberdrola in the German Baltic Sea.

First transformer has been delivered to convertor station for Dogger Bank Wind Farm. Image source Dogger Bank Wind Farm (pict. SSE Renewables)

The first of a number of transformers that will enable the transmission of renewable energy from the world’s largest offshore wind farm has been delivered. The transformers will play an integral role in the operation of three onshore convertor stations in East Riding of Yorkshire and on Teesside, that will eventually convert the current from the wind farm for transmission via the national grid network to 6 million UK homes.

The jacket, which will support the offshore platform substation, was secured on the seabed using the Saipem 7000 heavy lift vessel  (pict. SSE plc)

Construction of the world’s deepest fixed bottom offshore wind farm, which is also Scotland’s largest, has reached another milestone with the installation of a jacket in preparation for the project’s offshore substation topside which is due to be installed in early 2022.