Offshore wind project Rampion starts power generation

Tuesday, 28 November, 2017 - 11:30
The first of 116 MHI Vestas 3.45MW tubines has been commissioned at Rampion offshore wind farm. (Graphic: E.ON)
The first of 116 MHI Vestas 3.45MW tubines has been commissioned at Rampion offshore wind farm. (Graphic: E.ON)

The offshore wind farm Rampion in the English Channel has started generating electricity. According to E.ON, the first turbine was commissioned. 115 additional turbines will be connected to the grid in stages over the next few months.

The offshore work for the Rampion project began in autumn 2015 with the preparation of the seabed for the turbine foundations. The first monopile was installed at the beginning of 2016. The installation of the turbines began in March 2017 and was completed ahead of schedule in September.

The 400 megawatt Rampion project is located 13 kilometres off the Sussex coast. Owners are E.ON, the British Green Investment Rampion Ltd. and the Canadian energy company Enbridge. The project is being built and operated by E.ON as majority owner.

E.ON / Silke Funke

Similar Entries

Rostock-based company EEW Special Pipe Constructions GmbH has received an order from the Swedish energy group Vattenfall to produce 41 monopiles for the 344 MW offshore wind
farms Vesterhav. The contract was signed on 19 November 2021.

The first monopile for the Baltic Eagle offshore wind project is finished (pict. EEW SPC)

On 18 February 2022, the first monopile for the Baltic Eagle offshore wind farm was completed. The pile weighs 1,363 tonnes with a diameter of 9 metres. Baltic Eagle is already the second wind farm project of the Spanish energy company Iberdrola in the German Baltic Sea.

(l to r): Austin Coughlan, Head of Temporis Aurora Fund and Director of Inis Offshore Wind;  Vanessa O’Connell, Head of Inis Offshore Wind and Aoife Galvin, Senior Offshore Project Manager, Inis Offshore Wind, who joined from ESB (pict. ReputationInc)

Temporis Investment Management (“Temporis”) has on October 11th announced the launch of Inis Offshore Wind, a new Irish renewable energy firm with plans to develop at least 1GW of offshore wind capacity by 2030. This would constitute a significant contribution to Ireland’s offshore wind targets and provide enough electricity to power over 800,000 homes.

The jacket, which will support the offshore platform substation, was secured on the seabed using the Saipem 7000 heavy lift vessel  (pict. SSE plc)

Construction of the world’s deepest fixed bottom offshore wind farm, which is also Scotland’s largest, has reached another milestone with the installation of a jacket in preparation for the project’s offshore substation topside which is due to be installed in early 2022.